Test-Equipment Manufacture

We deliver exceptional construction with the highest level of quality through our specialized technology and proven project performance in the power plant industry.

Major Projects

  • POSRV Set Point Test Equipment
  • Turbin Overspeed Protection Device Performance Tester
  • TBN Governor Actuator / ETS System Service
  • EHPC Test Equipment
  • Safety Valve Test Bench
  • Filter Treatment System from Radioactive Contamination
  • Stud Hole Cleaning & NDE
  • Multi Stud Tensioner
  • Fuel Transfer Tube Closure
  • Generator Rotor Pulling(Insertion/Extraction) Device
  • No. Contract Title Clients Date Class
    1 Turbin Overspeed Protection Device Performance Tester KHNP Wolsong 2000.05-2006.06 S
    2 Turbin Overspeed Protection Device Performance Tester KHNP Hanul 2002.10-2002.11 S
    3 Turbin Overspeed Protection Device Performance Tester KHNP Wolsong 2004.10-2004.11 S
    4 Turbin Overspeed Protection Device Performance Tester KHNP Hanul 2005.09-2005.10 S
    5 Turbin Overspeed Protection Device Performance Tester KHNP Hanbit 2006.03-2006-04 S
    6 Hanbit Unit 2 / 26 O/H Turbine Hydraulic Solenoid Valve Maintenance Service KHNP Hanbit 2023.09-2023-11 Q
    7 Hanbit Unit 1 / 27th O/H Turbine Hydraulic Solenoid Valve Maintenance Service KHNP Hanbit 2023.11-2024-02 Q
    8 Saeul Unit 2 Turbine Hydraulic Solenoid Valve Maintenance Service KHNP Saeul 2024.02-2024-04 Q
    9 Hanbit Unit 4 / 17th O/H Turbine Hydraulic Solenoid Valve Maintenance Service KHNP Hanbit 2024.02-2024-04 Q
    10 Wolsong Unit 2 Turbine Hydraulic Solenoid Valve Maintenance Service KHNP Wolsong 2024.04-2024-07 A
    11 Hanul Unit 5,6 / 14th O/H Turbine Hydraulic Solenoid Valve Maintenance Service KHNP Hanul 2024.05-2025.05 Q
    12 Hanul Unit 5 Turbine Valve Actuator Maintenance/Performance Diagnosis Service KHNP Hanul 2024.07-2025.02 A
    13 Hanul Unit 3,4 Solenoid Valve Maintenance/Performance Diagnosis Service KHNP Hanul 2024.07-2025.02 A
    14 Hanul Unit 3,4 / EHPC Maintenance KHNP Hanul 2019.05-2020.02 A
    15 Shin-Kori Unit 1 / EHPC Maintenance KHNP Kori 2020.09-2020.10 A
    16 Shin-Kori Unit 1 / EHPC Maintenance KHNP Kori 2021.02-2021.04 A
    17 Hadong Unit 3 / BFPT EHPC Maintenance Korea Southern Power 2021.10-2021.11 S
    18 Shin-Kori Unit 1,2 / EHPC Maintenance KHNP Kori 2022.07-2022.11 A
    19 Hadong Unit 1 / BFPT EHPC Maintenance Korea Southern Power 2022.09-2022.10 S
    20 Hanbit Unit 5 / EHPC Maintenance KHNP Hanbit 2022.12-2023.04 A
    21 Filter Treatment System from Radioactive Contamination KEPCO KPS 2020.1 S
    22 Filter Treatment System from Radioactive Contamination KEPCO KPS 2022.03-2022.04 S
    23 Safety Valve Test Bench (2set) KHNP Shin-hanul 2023.05 S
    24 Safety Valve Test Bench KHNP Hanul 2023.02 S
    25 Safety Valve Test Bench KANGWOO CORP 2023.03 S
    26 LTOT valve Test Bench(Shin-Hanul) DOOSAN 2023.05 S
    27 Safety Valve Test Bench(Shin-Wolseong) SOOSAN IND 2024.03 S
    28 Safety Valve Test Bench KHNP Hanbit 2022.06 S
    29 Safety Valve Test Bench (Medium-2set) KHNP Hanul 2022.11 S
    30 Safety Valve Test Bench (Large) KHNP Hanbit 2022.11 S
    31 BNPP PJT LP Casing Working Platform DOOSAN-BNPP 2022.12 S
    32 Block, Calibration : 6EA, 6SET NAWAH-BNPP 2023.08 S
    33 Incheon ST1 Hydraulic Drive Valve Actuator Maintenance KOMIPO 2023.05 S
    34 Boryeong ST2 Hydraulic Drive Valve Actuator Maintenance KOMIPO 2023.05 S
    35 Reactor Protective Cover KHNP Shin-hanul 2024.01 S
    36 Radioactive Waste Filter Storage Production KHNP Wolsong 2024.04 S