No. | Contract Title | Clients | Date | Remark | Industry |
---|---|---|---|---|---|
1 | Wolseong Unit#1 Feeder Pipe Installation | KHNP Wolseong | 2010.02-2011.03 | Piping | Nuclear Power |
2 | Wolseong Unit#2 Pressure Tube Replacement | KHNP Wolseong | 2017.11-2018.06 | Piping | Nuclear Power |
3 | High Pressure Heavy Wall Pipe Replacement | KHNP Hanbit | 2013.12-2014.01 | Piping | Nuclear Power |
4 | Wolseong Unit#1 CFVS Installation Project | KHNP Wolseong | 2012.07-2013-02 | Piping | Nuclear Power |
5 | Monorail Installation | KHNP Hanul | 2006.09-2006.12 | Mechanic | Nuclear Power |
6 | Tank/heat Exchanger Manufacturing Work (22 types, 32 units) | DAEWOO E&C | 2005.01~2005.04 | Mechanic | Nuclear Power |
7 | Furnishing Electricians for Start-up Activities | GE | 2006.01~ 2006.07 | Mechanic | Nuclear Power |
8 | Compressed Air Supply Piping Improvement Work for Desulfurization Control | EWP-Ulsan | 2006.07~2006.07 | Piping | Thermal Power |
9 | Wolseong Unit #3 High-Pressure Water Heater Drainage Pipe Replacement | KEPCO KPS | 2006.02 | Piping | Nuclear Power |
10 | Wolseong Unit #4 High-Pressure Water Heater Drainage Pipe Replacement | KEPCO KPS | 2007.01-02 | Mechanic | Nuclear Power |
11 | Gas Storage Tank Manufacturing | SEAH E&C | 2007.01-10 | Mechanic | Nuclear Power |
12 | Wolseong Unit #2 Maintenance Convenience Facility Manufacturing/Installation | KEPCO KPS | 2007.03 | Mechanic | Nuclear Power |
13 | Shin-Kori Unit #1,2 Trolley Repair Work for Polar Crane | KHNP Kori | 2007.07-10 | Mechanic | Nuclear Power |
14 | Wolseong Unit #2 Turbine Building Operation and Maintenance Convenience Facilities | KHNP Wolseong | 2008.04-05 | Mechanic | Nuclear Power |
15 | Wolseong Unit #3 Coolant Heat Exchanger Front and Rear Valve Replacement | KHNP Wolseong | 2008.07 | Mechanic | Nuclear Power |
16 | Gimcheon Solar Power Plant 6MW Installation Work | SAMSUNG E&A | 2008.8-12 | Mechanic | Nuclear Power |
17 | Kori Unit #4 Secondary Seawater System Old Pipe Replacement | KHNP Kori | 2008.12-2009.01 | Piping | Nuclear Power |
18 | Wolseong Unit #1 Polluted Equipment Maintenance Room Construction | KEPCO KPS | 2009.04-07 | Mechanic | Nuclear Power |
19 | Wolseong Unit #1 Steam Drainage Piping Material Change | KHNP Wolseong | 2009.08-09 | Piping | Nuclear Power |
20 | Kori Unit #3 Secondary Seawater System Old Pipe Replacement | KHNP Kori | 2009.10-11 | Piping | Nuclear Power |
21 | Wolseong Unit #1 Equipment Cooling Water and Seawater System Facility Improvement | KEPCO KPS | 2009.12-2010.04 | Mechanic | Nuclear Power |
22 | Wolseong Unit #1 Upper Feeder Pipe Installation Work | KEPCO KPS | 2010.02-05 | Piping | Nuclear Power |
23 | Turbine Control Oil System Piping Replacement Work | DONGBU | 2010.06-07 | Piping | Nuclear Power |
24 | Yecheon Pumped Storage Power Plant Site Embedded Pipe Installation | EWP | 2007.8 | Piping | Pump Power |
25 | Pohang City Social Welfare Facility Solar Hot Water Facility Installation | Pohang City | 2009.12-2011.02 | Mechanic | General Industrial |
26 | Wolseong Unit #1 Reactor Pressure Pipe Replacement | KHNP Wolseong | 2011.01-06 | Piping | Nuclear Power |
27 | Housing Complex Welfare Center Construction of Wolseong KHNP HQ | KHNP Wolseong | 2010.03-2011.12 | Mechanic | General Industrial |
28 | Mechanical Equipment Construction of Wolseong Sports Center Construction | KHNP/SAEHAN | 2010.06-2011.11 | Mechanic | General Industrial |
29 | Wolseong Unit #2 Main Steam Piping Support Installation | KHNP Wolseong | 2012.09-10 | Piping | Nuclear Power |
30 | Wolseong Unit #1 R/B Underground Pipe Installation Cover Replacement | KHNP Wolseong | 2013.04 | Piping | Nuclear Power |
31 | Jordan Research and Training Reactor / Duck Production and Installation | Atomy Energy Co | 2014.06-2015.11 | Mechanic | Nuclear Power |
32 | Gimcheon Solar Power Plant 1 Module Structure Reinforcement | Cheil Industries | 2014.10-12 | Mechanic | Solar power |
33 | Gimcheon Solar Power Plant 2 Module Structure Reinforcement | Gimcheon Enerbix | 2014.10-12 | Mechanic | Solar power |
34 | Firefighting Equipment Construction of KHNP HQ | KHNP | 2014.05-2016-05 | Fire system | General Industrial |
35 | Wolseong Unit #2 Firefighting Equipment Replacement | KHNP Wolseong | 2016.1 | Fire system | Nuclear Power |
36 | Shin-Wolseong Unit #2 2nd O/H MSV, CV Surrounding Scaffolding Installation | KEPCO KPS | 2017.10-12 | Mechanic | Nuclear Power |
37 | Pyeongtaek Electronics P1-PJT Green Building/PH-2 Plumbing | SAMSUNG E&A | 2017.03-2018.07 | Mechanic | Semiconductor |
38 | Cheonan L5 Line Construction PJT Wastewater Pipe Demolition | SAMSUNG E&A | 2017.06-2018.04 | Piping | Semiconductor |
39 | Hanbit Unit #4 Nuclear Reactor Emergency Coolant External Injection Channel Installation | SOOSAN IND | 2017.05-2018.09 | Mechanic | Nuclear Power |
40 | Pyeongtaek Electronics P1-PJT Green Building/PH-3,4 Piping Work (B) | SAMSUNG E&A | 2017.10-2018.07 | Piping | Semiconductor |
41 | Pyeongtaek Electronics P2-PJT Green Building_[P2]PH1.Plumbing Work (A) | SAMSUNG E&A | 2018.08-2020.04 | Piping | Semiconductor |
42 | Pyeongtaek Electronics P-PJT Water Purification Plant MBR Piping Module Construction | SAMSUNG E&A | 2019.02-2020.08 | Piping | Semiconductor |
43 | CWP03 Discharge Pipe Replacement and Technical Support | SOOSAN IND | 2019.06-07 | Mechanic | Nuclear Power |
44 | Pyeongtaek Electronics P2-PJT Green Building_[P2] Lower East Piping Work (A) | SAMSUNG E&A | 2020.03-2023.07 | Piping | Semiconductor |
45 | Pyeongtaek Electronics P3 New Construction P3 Green Building Piping Work (A) | SAMSUNG E&A | 2021.03-2023.10 | Piping | Semiconductor |
46 | Urban Regeneration New Deal Project (Phase 2) Firefighting Construction | Sangju City | 2021.11-2023.11 | Fire system | General Industrial |
47 | Pyeongtaek Electronics P4 Green Building New Construction [P4] Sleeve Installation Work | SAMSUNG E&A | 2022.02-10 | Mechanic | Semiconductor |
48 | Pyeongtaek Electronics P4 Green Building New Construction Piping Work (A) | SAMSUNG E&A | 2022.09-2023.11 | Mechanic | Semiconductor |
49 | Pyeongtaek Electronics P4 Green Building New Construction [Ph.2] Plumbing Work (A) | SAMSUNG E&A | 2023.09-2024.07 | Mechanic | Semiconductor |